Contractors should be required by contract to prepare plans and procedures for tests they are contractually responsible for performing. The contractor should be required to submit the test plans and procedures for review and approval. A grantee representative (agency staff or supervised consultant) should perform a thorough review of the test plans and indicate whether they are acceptable before authorizing the contractor to proceed with testing. The contractor should be required to prepare test results and reports for review by grantee representatives. The grantee representative’s review should result in providing the contractor with written approval or rejection of the tested component or subsystem.